Kalpataru Parkcity Sector BReview of the public record: MahaRERA, prices and the land · Thane West
By June 2026 only the plinth was built, and the one building permit on record ran out on 6 May 2026. In March 2026 the promoter took ₹800 crore of new loans that its MahaRERA disclosure doesn’t show. Before you pay, ask for a building permit (CC) valid today, and which property those loans are secured on.
- MahaRERA
- 1 phase
- PR1332022500106
Key numbers
- Building permit
- Expired May 2026
- The only one on MahaRERA, issued 7 May 2025, was valid for one year; none later uploaded as of 8 Oct 2026
- Registered price per sq ft, 2026
- Steady
- Typical promoter sale, Jan–Mar vs Jul–Sep, from all 142 agreements registered for Towers 2A and 2B (IGR)
- Thane station
- 5.0 km
- Straight line; a ride, not a walk
- Mapped hazards nearby
- 1 kind
- What and how far: in the report
- Air quality, 24-hour average
- AQI 50
- Good · Upvan Fort · MPCB, 3.7 km away · 23 Sept, 9 pm
In the full report
- Ask your lawyer
The land
What stood here, decade by decade, and which records are missing.What this section looks like → - Old chemical belt
The neighbours
What they are, how far from the boundary, and in which direction.What this section looks like → - Permit lapsed on paper
The paperwork
Approvals, court orders and the occupation certificate, dated.What this section looks like → - Ask what the loans cover
The builder
Who stands behind it, and how its deadlines moved.What this section looks like → - Registered prices
The price
The locality trend, this project’s own sales, and what listings claim.What this section looks like → - Poor some winter days
The air
Each month’s best and worst days, and what the station can’t measure.What this section looks like → - Station by road
Getting around
Walks to the station and the main roads. Rush-hour drives: coming soon.What this section looks like → - High-risk ward
Rain and flooding
Which flood spots, year by year, and ten monsoons of rain.What this section looks like →
See what each section found.
- Opens the moment you pay
- Every line links to the public record it came from
- Refund if we can’t verify a line
- Independent: we don’t sell or broker property
Connectivity nearby
Trains
- Thane5.0 km, straight line
Main roads
- Ghodbunder Road1.8 km
- Eastern Express Highway2.1 km
- LBS Marg2.4 km
No metro station open nearby yet. Line 4 on Ghodbunder Road is not open as of Sep 2026. Walks are estimates (straight line × 1.3, at 4.5 km/h); road distances are straight line. Rush-hour drive times are coming soon.
Other projects nearby
Straight-line distance
- Piramal Vaikunth Cluster 3950 m · Full report ready
Check it yourself
Free buyer guidesCompare side by side
Show · Pick a second project on the map
Pick a second project to see its numbers next to Kalpataru Parkcity Sector B’s.