Marathon Neopark AshokaReview of the public record: MahaRERA, prices and the land · Bhandup West
Wing A’s MahaRERA registration has lapsed with no new date, and Wing C’s date has moved 34 months, far beyond MahaRERA’s 4-month extension. Before you pay for Wing A, ask for its renewed MahaRERA registration and new completion date.
- MahaRERA
- 2 phases
- P51800031073, P51800030752
Key numbers
- Registered price per sq ft, 2026
- +0.5%, then -0.2%
- Quarter on quarter, Feb–Mar to Jul–Sep: typical Wing C flat sale by the promoter, from IGR registrations
- Wing A’s registration
- Lapsed
- Due 31 Dec 2025; no new date on MahaRERA as of 1 Oct 2026
- Walk to Nahur station
- ~30 min
- Estimate: straight line × 1.3, at 4.5 km/h
- Mapped hazards within 2 km
- 1 kind
- What and how far: in the report
- Air quality, 24-hour average
- AQI 60
- Satisfactory · Khindipada-Bhandup West · IITM, 1.1 km away · 23 Sept, 9 pm
In the full report
- Title clear
The land
What stood here, decade by decade, and which records are missing.What this section looks like → - Pipeline and workshops
The neighbours
What they are, how far from the boundary, and in which direction.What this section looks like → - Wing A has lapsed
The paperwork
Approvals, court orders and the occupation certificate, dated.What this section looks like → - Ask about newer loans
The builder
Who stands behind it, and how its deadlines moved.What this section looks like → - Registered prices
The price
The locality trend, this project’s own sales, and what listings claim.What this section looks like → - Moderate in winter
The air
Each month’s best and worst days, and what the station can’t measure.What this section looks like → - Away from the station
Getting around
Walks to the station and the main roads. Rush-hour drives: coming soon.What this section looks like → - Flood-prone roads nearby
Rain and flooding
Which flood spots, year by year, and ten monsoons of rain.What this section looks like →
The Marathon Neopark Ashoka report: 6 findings from the public record
- Wing AIn the reportAsk for the new date
- Wing CIn the reportFar beyond Order 66
- ProgressIn the reportCheck your wing
- MortgageIn the reportAsk about newer loans
- ComplaintsIn the reportRead the orders
- PriceIn the reportRegistered prices
₹999 one-time · opens the moment you pay
Every line links to its public record · refund if we can’t verify a line · we don’t sell or broker property
Not ready to buy? Get the 5 questions to ask before you register, free by email.
Possession date on MahaRERA
Read 28 Sept 2026
Marathon Neopark Ashoka’s completion date on MahaRERA has moved 33 months, from Dec 2025 to Oct 2028.
| RERA no. | First date | Now |
|---|---|---|
| P51800030752 | Dec 2025 | Oct 2028 (+33 mo) |
This is the builder’s own deadline for finishing, as registered. Possession follows the building’s Occupation Certificate. Check it yourself: MahaRERA project search · has the date moved? · OC and CC · carpet area · stamp duty
Connectivity nearby
Trains
- Nahur~30 min walk
- Bhandup~37 min walk
Main roads
- LBS Marg0.6 km
- Eastern Express Highway2.7 km
No metro station open nearby yet. Line 4 on LBS Marg is not open as of Sep 2026. Walks are estimates (straight line × 1.3, at 4.5 km/h); road distances are straight line. Rush-hour drive times are coming soon.
Other projects nearby
Straight-line distance
- Marathon Neosquare100 m · Bhandup West · Full report ready
- Vanita Sadan CHS250 m · Bhandup West · Completion date moved 4 months
- Advent Neel Residency500 m · Bhandup West · No date revision on record
- Godrej Nurture500 m · Bhandup West · Full report ready
- Om Siddhivinayak CHS650 m · Bhandup West · No date revision on record
Check it yourself
Free buyer guidesCompare side by side
Show · Pick a second project on the map
Pick a second project to see its numbers next to Marathon Neopark Ashoka’s.