Marathon Neopark AshokaReview of the public record: MahaRERA, prices and the land · Bhandup West

Wing A’s MahaRERA registration has lapsed with no new date, and Wing C’s date has moved 34 months, far beyond MahaRERA’s 4-month extension. Before you pay for Wing A, ask for its renewed MahaRERA registration and new completion date.

MahaRERA
2 phases
P51800031073, P51800030752

Key numbers

Registered price per sq ft, 2026
+0.5%, then -0.2%
Quarter on quarter, Feb–Mar to Jul–Sep: typical Wing C flat sale by the promoter, from IGR registrations
Wing A’s registration
Lapsed
Due 31 Dec 2025; no new date on MahaRERA as of 1 Oct 2026
Walk to Nahur station
~30 min
Estimate: straight line × 1.3, at 4.5 km/h
Mapped hazards within 2 km
1 kind
What and how far: in the report
Air quality, 24-hour average
AQI 60
Satisfactory · Khindipada-Bhandup West · IITM, 1.1 km away · 23 Sept, 9 pm

In the full report

The Marathon Neopark Ashoka report: 6 findings from the public record

  • Wing AIn the reportAsk for the new date
  • Wing CIn the reportFar beyond Order 66
  • ProgressIn the reportCheck your wing
  • MortgageIn the reportAsk about newer loans
  • ComplaintsIn the reportRead the orders
  • PriceIn the reportRegistered prices

₹999 one-time · opens the moment you pay

The Marathon Neopark Ashoka report

₹999

  • What we found in every section, with the source for each line.
  • Opens as soon as you pay, and the link is emailed to you.
  • Refund if we can’t verify a line.

UPI, cards or netbanking, through Razorpay.

See a sample report

Every line links to its public record · refund if we can’t verify a line · we don’t sell or broker property

Not ready to buy? Get the 5 questions to ask before you register, free by email.

Free. No calls, no spam. We don’t sell property.

Possession date on MahaRERA

Read 28 Sept 2026

Marathon Neopark Ashoka’s completion date on MahaRERA has moved 33 months, from Dec 2025 to Oct 2028.

Marathon Neopark Ashoka: completion dates on the MahaRERA register
RERA no.First dateNow
P51800030752Dec 2025Oct 2028 (+33 mo)

This is the builder’s own deadline for finishing, as registered. Possession follows the building’s Occupation Certificate. Check it yourself: MahaRERA project search · has the date moved? · OC and CC · carpet area · stamp duty

Connectivity nearby

Trains

  • Nahur~30 min walk
  • Bhandup~37 min walk

Main roads

  • LBS Marg0.6 km
  • Eastern Express Highway2.7 km

No metro station open nearby yet. Line 4 on LBS Marg is not open as of Sep 2026. Walks are estimates (straight line × 1.3, at 4.5 km/h); road distances are straight line. Rush-hour drive times are coming soon.

Other projects nearby

Straight-line distance

All projects in Bhandup

Check it yourself

Free buyer guides

Compare side by side

Show · Pick a second project on the map

Pick a second project to see its numbers next to Marathon Neopark Ashoka’s.