Marathon NeosquareReview of the public record: MahaRERA, prices and the land · Bhandup West
Due in December 2022, its completion date now says April 2027, and MahaRERA has passed orders on four complaints against the promoter. Before you pay, ask when the occupation certificate is expected, and get a fixed possession date in your agreement.
- MahaRERA
- 1 phase
- P51800010386
Key numbers
- Completion date
- Moved 52 months
- Dec 2022 → Apr 2027 on MahaRERA, well beyond the 4 months MahaRERA gave every project in Aug 2026
- Complaints
- 4
- Against the promoter on MahaRERA, 2024–25, with orders passed
- Walk to Nahur station
- ~30 min
- Estimate: straight line × 1.3, at 4.5 km/h
- Mapped hazards within 2 km
- 1 kind
- What and how far: in the report
- Air quality, 24-hour average
- AQI 60
- Satisfactory · Khindipada-Bhandup West · IITM, 1.1 km away · 23 Sept, 9 pm
In the full report
- Slum-scheme land
The land
What stood here, decade by decade, and which records are missing.What this section looks like → - Pipeline and workshops
The neighbours
What they are, how far from the boundary, and in which direction.What this section looks like → - 52 months late
The paperwork
Approvals, court orders and the occupation certificate, dated.What this section looks like → - Four complaints
The builder
Who stands behind it, and how its deadlines moved.What this section looks like → - Few sales to go on
The price
The locality trend, this project’s own sales, and what listings claim.What this section looks like → - Moderate in winter
The air
Each month’s best and worst days, and what the station can’t measure.What this section looks like → - Away from the station
Getting around
Walks to the station and the main roads. Rush-hour drives: coming soon.What this section looks like → - Flood-prone roads nearby
Rain and flooding
Which flood spots, year by year, and ten monsoons of rain.What this section looks like →
The Marathon Neosquare report: 6 findings from the public record
- CompletionIn the reportFar beyond Order 66
- ProgressIn the reportAsk about the OC
- Building permitIn the reportAsk for the 2022 CC
- ComplaintsIn the reportRead the orders
- MortgageIn the reportAsk about newer loans
- PriceIn the reportFew sales; about 9 flats left
₹999 one-time · opens the moment you pay
Every line links to its public record · refund if we can’t verify a line · we don’t sell or broker property
Not ready to buy? Get the 5 questions to ask before you register, free by email.
Possession date on MahaRERA
Read 28 Sept 2026
Marathon Neosquare’s completion date on MahaRERA has moved 52 months, from Dec 2022 to Apr 2027.
| RERA no. | First date | Now |
|---|---|---|
| P51800010386 | Dec 2022 | Apr 2027 (+52 mo) |
This is the builder’s own deadline for finishing, as registered. Possession follows the building’s Occupation Certificate. Check it yourself: MahaRERA project search · has the date moved? · OC and CC · carpet area · stamp duty
Connectivity nearby
Trains
- Nahur~30 min walk
- Bhandup~38 min walk
Main roads
- LBS Marg0.6 km
- Eastern Express Highway2.7 km
No metro station open nearby yet. Line 4 on LBS Marg is not open as of Sep 2026. Walks are estimates (straight line × 1.3, at 4.5 km/h); road distances are straight line. Rush-hour drive times are coming soon.
Other projects nearby
Straight-line distance
- Marathon Neopark Ashoka100 m · Bhandup West · Full report ready
- Vanita Sadan CHS300 m · Bhandup West · Completion date moved 4 months
- Godrej Nurture500 m · Bhandup West · Full report ready
- Advent Neel Residency550 m · Bhandup West · No date revision on record
- Om Siddhivinayak CHS600 m · Bhandup West · No date revision on record