Buyer guide · Mumbai

How to check if a MahaRERA project’s completion date has moved

Find a Mumbai project’s original and revised completion dates on MahaRERA in five minutes, what to ask if it moved, and what we found across Kanjurmarg and Bhandup.

Updated · Not legal advice

1Find the project’s MahaRERA page

Each phase or wing of a project has its own registration and its own dates, so start from the right number.

Time
5 min
Cost
Free

How to check

  1. Get the registration number from the builder or any advertisement. Mumbai numbers look like P51800012345 or PR1180002400022.
  2. On MahaRERA, open the search for registered projects and enter the number (or the project’s name).
  3. Type the CAPTCHA and open the project.
  4. Check the project name and wing match the flat you’re being offered.

2Read the two dates

The original date is what the builder declared when the project registered. The revised date is where it stands now.

Time
2 min per wing

How to check

  1. Near the top of the page, find Proposed Completion Date (Original).
  2. Just below, find Proposed Completion Date (Revised).
  3. Count the months between them. That is how far completion has moved.
  4. For a project with several wings, repeat for each registration: they often move by different amounts.

Example from our records: Wing M of Runwal Avenue, Kanjurmarg East, went from Apr 2026 (original) to Feb 2029 (revised), a move of 34 months. Its other wings moved 4 to 16 months.

3If the date has moved, ask why

The Act lets MahaRERA extend a project’s registration (section 6). Short moves are common, and some come from extensions granted to projects generally during COVID-19. Long ones need an explanation.

Questions for the builder

  1. Why did the completion date move, and is there an extension order? Ask to see it.
  2. Which date will be in my agreement for sale: the original or the revised one?
  3. What does the latest architect’s progress certificate (Form 1) say is complete?

Watch out for

  • A sales-office possession date earlier than MahaRERA’s revised date.
  • A date that has moved more than once, or by years rather than months.
  • Progress certificates that barely change between filings.

4If possession is late

Section 18 of the Act gives buyers remedies when a builder fails to hand over possession by the date in the agreement for sale.

  • Withdraw: get your money back with interest.
  • Stay: get interest for every month of delay until possession.
  • Complaints are filed with MahaRERA. Ask a lawyer before you act: this guide is not legal advice.

What we found in Kanjurmarg and Bhandup

We read the MahaRERA page of every recently updated registration in these two areas: 76 registrations for 63 projects, read on 28 Sept 2026.

68 of 76

registrations have moved

89% of those we read

31

moved a year or more

16

moved more than two years

4 months

typical move

half the moves were this or less

How far the date movedRegistrations
Not moved8
1–6 months35
7–12 months8
13–24 months9
More than 2 years16

Months are counted from the original to the revised date on each registration. Every project, with its dates, is on our area pages: Kanjurmarg and Bhandup.

The checklist

CheckWhereTime
Find the registration for your wingMahaRERA5 min
Original vs revised completion dateMahaRERA project page2 min
Ask why it moved; see the extension orderBuilder—
Match the agreement’s date to MahaRERA’sDraft agreement10 min

Skip the searching

For every project on our maps, the project page already shows each wing’s original and revised dates, units sold and unsold, and complaints on MahaRERA. Free, no sign-up.

Kanjurmarg projectsBhandup projects

More checks before you pay: what to check before the token.

Sources

  • The Real Estate (Regulation and Development) Act, 2016: sections 6 and 18.
  • MahaRERA project pages, maharera.maharashtra.gov.in, read 28 Sept 2026.